Risk-Oriented Methodology for Contractor Management in the Construction of Optical Lines, Including Modeling of Crew Productivity and Logistics Delays in PERT/CPM Networks and Calibration of Contractual Incentives/Penalties

Mykola Gomzov

Open source

DOI
10.59324/ejiss.2025.1(6).09
Published
2025-11-27
Container
European Journal of Innovative Studies and Sustainability
Publisher
Not recorded
Open access
yes

Credibility signals

limited evidence Score 45/100 under policy 1.0.0. This is a metadata assessment, not a judgment of the paper's conclusions.

Show all credibility signals

Cite this work

BibTeX

@article{allodium:10.59324/ejiss.2025.1-6-.09,
  title = {Risk-Oriented Methodology for Contractor Management in the Construction of Optical Lines, Including Modeling of Crew Productivity and Logistics Delays in PERT/CPM Networks and Calibration of Contractual Incentives/Penalties},
  author = {Mykola Gomzov},
  year = {2025},
  journal = {European Journal of Innovative Studies and Sustainability},
  doi = {10.59324/ejiss.2025.1(6).09},
  url = {https://doi.org/10.59324/ejiss.2025.1(6).09}
}

RIS

TY  - JOUR
TI  - Risk-Oriented Methodology for Contractor Management in the Construction of Optical Lines, Including Modeling of Crew Productivity and Logistics Delays in PERT/CPM Networks and Calibration of Contractual Incentives/Penalties
AU  - Mykola Gomzov
PY  - 2025
JO  - European Journal of Innovative Studies and Sustainability
DO  - 10.59324/ejiss.2025.1(6).09
UR  - https://doi.org/10.59324/ejiss.2025.1(6).09
ER  - 

APA

Gomzov, M. (2025). Risk-Oriented Methodology for Contractor Management in the Construction of Optical Lines, Including Modeling of Crew Productivity and Logistics Delays in PERT/CPM Networks and Calibration of Contractual Incentives/Penalties. European Journal of Innovative Studies and Sustainability. https://doi.org/10.59324/ejiss.2025.1(6).09

Source records